Technology and Application of Temporary Invert With Detachable Components in Tunnels

CHEN Shihao1, 2, DAI Qinghua1, CHEN Peishuai1, 2, YUAN Qing1, 2, *, XIONG Qihuan1, 2, YANG Zhao1, 2   

  1. (1. CCCC Second Harbor Engineering Company Ltd., Wuhan 430040, Hubei, China; 2. Key Laboratory of Large-span Bridge Construction Technology, Wuhan 430040, Hubei, China)
  • Online:2023-10-20 Published:2023-11-08

Abstract: The traditional temporary invert constructed by Isteel + shotcrete is complex in the construction process. Moreover, its construction quality is greatly affected by human factors and cannot be reused. Therefore, a novel detachable concretefilled steel tube temporary invert and its supporting structure, designed for easy and rapid disassembly, are proposed. The structures are tested and applied to the highspeed Zongka #2 tunnel of the TongrenSaierlong railway. The steel pipe has an outer diameter of 108 mm and a wall thickness of 8 mm, and is filled with C30 fine stone concrete. The detachable components comprise a sleeve and a builtin wedgeshaped unloading block, and the concretefilled steel tubes are inserted from both sides to achieve segment connection. Field application results reveal the following: (1) The proposed temporary invert structure is safe, reliable, and feasible and can realize factory prefabrication and quick disassembly on site. The proposed temporary invert can improve construction efficiency by 643% and reduce the settlement deformation rate of the arch and peripheral convergence rate by 657%~661% and 746%~795%, respectively, compared to the traditional temporary invert constructed by I-steel + shotcrete. (2) The axial force value measured during the operation of the structure is less than the calculated and designed ones, indicating that the structure is in a safe state. The reutilization rates of the segment and detachable structure are up to 94.5% and 100%, respectively.

Key words: tunnel, detachable components, temporary invert, concretefilled steel tube, quick disassembly and assembly, recycling