铁路隧道软弱围岩大断面机械化施工经济性研究与分析

吴炜1, 覃伟华1, 罗福君2   

  1. 1. 中国铁路经济规划研究院有限公司, 北京 100038 2. 中铁二院工程集团有限责任公司, 四川 成都 610031
  • 出版日期:2020-12-20 发布日期:2021-01-03
  • 作者简介:吴炜(1989—),男,北京人,2015年毕业于中国矿业大学(北京),建筑与土工工程专业,硕士,工程师,现主要从事铁路隧道造价标准研究、编制工作。E-mail: 191919812@qq.com。

Economic Analysis on Large Crosssectional Mechanized Construction of Soft Rock Railway Tunnel

WU Wei1, QIN Weihua1, LUO Fujun2   

  1. (1. China Railway Economic and Planning Research Institute Co., Ltd., Beijing 100038, China; 2. China Railway Eryuan Engineering Group Co., Ltd., Chengdu 610031, Sichuan, China)

  • Online:2020-12-20 Published:2021-01-03

摘要: 为分析铁路隧道软弱围岩大断面机械化施工经济性的影响因素,以及各因素的影响程度,依据郑万高铁软弱围岩大断面机械化施工和普通机械化施工(台阶法)2套设计图的工程量,结合现行铁路造价标准与部分软弱围岩大断面机械化配套工艺单价分析,编制3套概算方案从工程量优化和工艺工法变化2个方面进行对比研究。研究结果表明: 1)影响大断面机械化施工经济性的主要因素是超前加固; 2)Ⅳa、Ⅳb、Ⅴa级围岩大断面机械化施工较普通机械化施工延米概算指标分别增长了-9.41%10.81%和6.24% 3)Ⅳ、Ⅴ级围岩大断面机械化施工较普通机械化施工月进尺分别提高了9.33%22.22%,体现出一定的综合经济性。

关键词: 铁路隧道, 软弱围岩, 大断面, 机械化施工, 经济性, 工程量, 工艺工法

Abstract: The influencing factors and their influencing degree of economy of large crosssectional mechanized construction of soft rock railway tunnel are of great significance. As a result, the construction quantities of two mechanized construction design drawings, i.e. the large crosssectional mechanized construction and conventional mechanized construction(bench method) of soft rock tunnel of ZhengzhouWanzhou Highspeed Railway, are introduced, and three sets of budgeting schemes are established from aspects of quantity optimization and technology variation based on existing railway cost standard and partial unit price analysis on large crosssectional mechanized construction of soft surrounding rock. The research results show that: (1) The advance reinforcement is the main economic affecting factor of large crosssectional mechanized construction. (2) Compared with the conventional mechanized construction method, the budgeting index per meter of large crosssectional mechanized construction in Grade Ⅳa, Ⅳb and Ⅴa surrounding rocks increases by -9.41%, 10.81% and 6.24% respectively; and the monthly advance of large crosssectional mechanized construction in Grade and surrounding rocks increases by 9.33% and 22.22% respectively, which shows obvious economy.

Key words: railway tunnel, soft surrounding rock, large crosssection, mechanized construction, economy, construction quantity, construction method