摘要:
结合乌兹别克斯坦安—琶铁路隧道施工实际情况,按机械化配套施工方案进行了全隧道的设备配置,通过过程调整和测定等方式,成功在该隧道实践应用,达到了较高的施工水平,在施工周期内实现了单头掘进平均200 m/月的施工进度,达到了预期的施工目标。通过本项目机械化配套的实践应用,解决了单线铁路隧道施工无法实现全机械化配套的难题。
关键词: 单线铁路隧道, 机械化配套
Abstract:
The mechanization matching program has been successfully used in construction of AngrenPap Singleline Railway Tunnel in Uzbekistan, and good effects have been achieved. The paper can provide reference for mechanization matching of similar projects in the future.
Key words: singleline railway tunnel, mechanization matching
中图分类号:
U 45
谢大文, 刘一, 王华. 单线铁路隧道机械化配套方案在乌兹别克斯坦安—琶铁路隧道的实践应用[J]. 隧道建设, 2015, 35(S2): 181-186.
XIE Dawen, LIU Yi, WANG Hua. Application of Mechanization Matching Program in AngrenPap Singleline Railway Tunnel in Uzbekistan[J]. Tunnel Construction, 2015, 35(S2): 181-186.
0 / / 推荐
导出引用管理器 EndNote|Ris|BibTeX
链接本文: http://www.suidaojs.com/CN/10.3973/j.issn.1672-741X.2015.S2.033
http://www.suidaojs.com/CN/Y2015/V35/IS2/181