• 中国科学引文数据库(CSCD)来源期刊
  • 中文核心期刊中文科技核心期刊
  • Scopus RCCSE中国核心学术期刊
  • 美国EBSCO数据库 俄罗斯《文摘杂志》
  • 《日本科学技术振兴机构数据库(中国)》
二维码

隧道建设(中英文) ›› 2016, Vol. 36 ›› Issue (8): 947-952.DOI: 10.3973/j.issn.1672-741X.2016.08.009

• 研究与探索 • 上一篇    下一篇

拱北隧道工程中曲线顶管顶进力实测分析

谈力昕, 张鹏, 谢红明, 马保松   

  1. (中国地质大学(武汉)工程学院, 湖北 武汉 430074)
  • 收稿日期:2016-01-04 修回日期:2016-03-17 出版日期:2016-08-20 发布日期:2016-08-17
  • 作者简介:谈力昕(1992—),男,江苏常州人,中国地质大学(武汉)地质工程专业在读硕士,主要研究方向为顶管与非开挖工程的设计。Email: 1245210321@qq.com。

Analysis of Jacking Force of Curved Pipe Jacking in Gongbei Tunnel

TAN Lixin, ZHANG Peng, XIE Hongming, MA Baosong   

  1. (Faculty of Engineering, China University of Geosciences, Wuhan 430074, Hubei, China)
  • Received:2016-01-04 Revised:2016-03-17 Online:2016-08-20 Published:2016-08-17

摘要:

港珠澳大桥珠海连接线拱北隧道工程口岸暗挖段采用曲线顶管管幕支护的施工方法,在复杂地层条件下计算曲线顶管顶进力是顶管施工的重点与难点。工程共计使用了37根外径为1 620 mm、平均长度约为255 m的钢顶管。结合现场施工记录,采用2种不同的计算方式对顶进力进行了估算并与实际顶进力进行对比验证。结果表明: 经验公式中的摩阻力计算在埋深较大时比较符合实际情况,在浅层的淤泥质地层中则偏大;直接采用被动土压力计算迎面阻力是偏保守的;顶进力的大小与泥浆润滑关系密切,初始阶段泥浆的润滑作用并不显著,在形成稳定的泥浆套过程当中摩阻力会逐渐下降,甚至小于1 kN/m2。

关键词: 港珠澳大桥, 拱北隧道, 曲线顶管, 顶进力, 迎面阻力, 摩阻力

Abstract:

The pipe curtain retaining method of curved pipe jacking is applied to the construction of mined section of Gongbei Tunnel, which is a significant part of Hong KongZhuhaiMacao Bridge Connecting Project. The estimation of total jacking force in curved alignment still remains its necessity and difficulty especially when driving in complex ground. A total of 37 steel pipelines with diameter of 1 620 mm and average length of 255 m are installed around the tunnel section as an advance support. Two different calculation methods, including an empirical formula and a theoretical formula are used to estimate the jacking force and compare with the insite driving force. The results indicate that: 1) The friction force calculated by empirical formula coincides with actual friction force in deep buried condition; however, it is larger than actual friction force in shallow silty ground. 2) Compared with the measured penetration load, the calculated passive earth pressure is more conservative. 3) The slurry shows a significant influence on the jacking force, but not so obvious in the initial stage of jacking; however, when a continuous and complete slurry jacket is formed, the friction force reduces (lower than 1 kN/m2).

Key words: Hong KongZhuhaiMacao Bridge, Gongbei Tunnel, curved pipe jacking, jacking force, penetration load, frictional resistance

中图分类号: