隧道建设(中英文) ›› 2007, Vol. 27 ›› Issue (6): 36-38.DOI: B
苏利军, 刘立新
SU Li-Jun, Liu-Li-Xin
摘要:
Due to the rigorous time limit of drain tunnel in JinpingII Hydropower Project, compact plane layout that can satisfy the requirements of quick TBM assemble is designed for the TBM assemble cavern, minimal crosssection that can satisfy the assemble is designed, reinforcement pattern consisting of rock bolts, shotcreting and wire meshing is designed. The design plan of the TBM assemble cavern is favorable for the ontime boring the TBM.
中图分类号: