ISSN 2096-4498

   CN 44-1745/U

二维码

Tunnel Construction ›› 2012, Vol. 32 ›› Issue (3): 377-382.DOI: 10.3973/j.issn.1672-741X.2012.03.021

• wenzhang • Previous Articles     Next Articles

Application and Optimization of Horizontal Jet Grouting Piles in Construction of Tunnels in Waterrich Soft Rock Ground

YU Zhongbo1, LI Shijun2, SHI Longyan2   

  1. (1. China Railway Tunnel Group Co., Ltd., Luoyang 471009, Henan, China;  2. The 2nd Engineering Co., Ltd. of China Railway Tunnel Group, Sanhe 065201, Hebei, China)
  • Received:2012-03-05 Revised:2012-04-12 Online:2012-06-20 Published:2012-07-09

Abstract: K15+838.35~+660 section of the trial section of the first phase of line M3 of Qingdao Metro, with 8.15~13.1 m overburden, runs through Grade VI waterrich sand strata. Furthermore, the tunnel section has complex ground surface environment. Therefore, there is great risk in the construction of the tunnel section. However, dewatering and vertical reinforcement can not be executed from the ground surface. Therefore, horizontal jet grouting piles, as well as a series of advance reinforcement technologies are adopted, so as to guarantee the safety of the surface buildings and the tunneling labors. The disadvantage of horizontal jet grouting piles in sand strata and crushed stone strata, i.e., failure in interlocking, is solved, which guarantees the safety of tunneling in waterrich soft ground.

Key words: Metro tunnel in waterrich soft ground, horizontal jet grouting pile, waterrich sand strata, pile interlocking, grouting through advance small duct