Overbreak/shortbreak Control Technology for and Cost Analysis on Rock Tunnels Constructed by Drilling and Blasting Method: Case Study on Tunnels on JiujiangRuichang Highway

FENG Haibao1,2, JIANG Wande1, QU Lili1, GUO Qingjie3   

  1. (1. The Second Engineering Co., Ltd., of CCCC First Harbor Engineering Co., Ltd., Qingdao 266071, Shandong, China; 2. Shandong University, Jinan 250101, China;3. General Contract Branch of CCCC First Harbor Engineering Co., Ltd., Tianjin 300461, China)
  • Received:2012-07-16 Revised:2012-08-03 Online:2012-12-20 Published:2012-12-28

Abstract: The stateofart of overbreak/shortbreak in tunneling is presented, the causes for overbreak/shortbreak are analyzed, and the influences of overbreak/shortbreak on the tunneling cost are described, so as to reduce the cost induced by overbreak/shortbreak of rock tunnels constructed by drilling and blasting method and to improve the qualification rate of tunnel excavation. Effective overbreak/shortbreak control technologies are determined on basis of investigations and trials. After these technologies are applied, the average qualification rate in tunnel excavation has been raised from 67.4% to 83.9%, and the economic efficiency has been improved by 49.9%, which demonstrates that the technologies applied are effective. The paper can provide reference for similar projects in the future.

Key words: JiujiangRuichang highway, rock tunnel, drilling and blasting method, overbreak/shortbreak, control technology, cost