Abstract:
The TBM often jammed due to the overlarge thrusting force and torque induced by collapse of working face and overlarge mucking during TBM boring in waterrich and silty sand stratum. The ground ahead of cutter head is grouting consolidated, so as to successfully disassembling the jammed TBM. The watercontaining rate of the ground is reduced, the stability of the ground is improved and the successful and safe disassembling of cutter head is guaranteed.
Key words: water rich, silty sand, sand bursting, TBM jamming, cutter head, grouting consolidation
GE Zhaihui. Grouting Consolidation Technologies for Disassembling Jammed TBM Cutter Head in Waterrich and Silty Sand Stratum[J]. Tunnel Construction, 2012, 32(增刊2): 105-110.
0 / / Recommend
Add to citation manager EndNote|Ris|BibTeX
URL: http://www.suidaojs.com/EN/10.3973/j.issn.1672-741X.2012.z2.021
http://www.suidaojs.com/EN/Y2012/V32/I增刊2/105