Due to the special engineering environment and construction technology of Liuyingmen StationWufutang Station shield section of Phase 3 of Beijing Metro Line No. 8, the conventional geological prediction method is hard to be carried out. The characteristics of phase position and vibration amplitude of seismic wave are analyzed by regarding the cutting vibration of shield cutterhead as vibration source and seismic reflection method as principle; the advanced geological prediction method based on seismic reflection method for shield tunneling is proposed; and then the advanced geological prediction and relevant tracking work are carried out. The field test shows that: 1) The abovementioned geological prediction method is easy in layout and convenient in operation and does not affect shield advancing. 2) The shapes and contours of underground bodies can be well reflected by the abovementioned geological prediction method, and the interpretation of the prediction results coincides with the actual data.
Key words: shield tunneling, advanced geological prediction, seismic reflection method, forward modeling
CLC Number:
U 452.1+1
HOU Weiqing, ZHANG Xingyu, YE Ying. Preliminary Study of Advanced Geological Prediction Based on Seismic Reflection Method for Shield Tunneling[J]. Tunnel Construction, 2017, 37(8): 1003-1010.
0 / / Recommend
Add to citation manager EndNote|Ris|BibTeX
URL: http://www.suidaojs.com/EN/10.3973/j.issn.1672-741X.2017.08.014
http://www.suidaojs.com/EN/Y2017/V37/I8/1003