ISSN 2096-4498

   CN 44-1745/U

二维码

Tunnel Construction ›› 2018, Vol. 38 ›› Issue (8): 1384-1390.DOI: 10.3973/j.issn.2096-4498.2018.08.016

Previous Articles     Next Articles

Research and Application of A New Type of Digital  Tunnel Lining Trolley with Pressured Casting

JI Haidong, LIU Zaizheng, ZHANG Haitao   

  1. (China Railway Construction Heavy Industry Co., Ltd., Changsha 410100, Hunan, China)
  • Received:2018-04-18 Revised:2018-07-16 Online:2018-08-20 Published:2018-09-04

Abstract:

The construction of tunnel lining by traditional lining trolley has many disadvantages such as concrete leakage, large vibration intensity and easy damage of connection point, etc. Hence, a new type of digital tunnel lining trolley with pressured casting is developed based on equipment design and informatized design to reduce lining hollows, cracks and drops. The trolley is equipped with doublecasting technology, pressintomold technology, highfrequency vibrating technology, connecting by special elastic material (soft connection technology), and digital control technology. The trolley has been applied firstly to Luojiashan Tunnel in Hubei, and good effects have been achieved. The doublecasting system can reduce the casting time from 12 h to 8 h, and the highfrequency vibrating can tamp concrete fully and reduce the bubbles, which can improve the concrete quality and reduce the labor intensity. Meanwhile, the mechanization, informatization and intellectualization of lining construction have been realized to a certain extent by the application of information integrated transmission system.

Key words: tunnel, digital lining trolley, pressured casting, highfrequency vibrating, casting system, control system, connecting by special elastic material (soft connection)

CLC Number: