The Construction Technology and the Main Equipments
selection of Insitu Placed Wall

JIAO Lei, JIANG Zhong-Quan   

  1. The 4th municipal works branch of Sanchu Co.,Ltd. of China Railway Tunnel Group, Shanghai 200127|China
  • Received:2005-05-08 Online:2005-12-20 Published:2009-12-19

Abstract:

Taking the construction of the underground diaphragm walls of Longyanglu station of line 6 of the Shanghai's MRT system as example, the author describes the construction process, construction technology and selection of major construction equipment of the construction of the diaphragm walls by means of hoistingassembling method.

Key words: diaphragm wall, equipment selection, construction technology