Development Features and Treatment of Karsts along
No. 1 Gaoping Tunnel on YiWan Railway

LI Ming-Chong,  Zhang-Min-Qiang, LI Dai-Ren   

  1. 1.China Railway the 4th Survey &|Design Institute2.Scientific Research Institute of China Railway Tunnel Group Co., Ltd.3. YiWan Railway Construction Headquarters
  • Received:2006-05-11 Online:2006-06-20 Published:2009-12-09

Abstract:

No. 1 Gaoping tunnel on YiWan railway passes through T21j limestone. The tunnel is located in verticalcirculating karst zones, with the maximum overburden being 104m. The karsts along the tunnel are extremely developed, with a total of 51 karst caves having been discovered during the construction of the tunnel. By means of analysis on the karst caves discovered during the tunnel construction, the article makes a study on the features of the development of the karsts located in verticalcirculating zones. On basis of the features of the development of the karsts and the characteristics of the engineering structures, the article suggests a karst scale determination standard, recommends some karst treatment measrues and makes an assessment on the effect of the karst treatment.

Key words:  , verticalcirculating zone karst development feature  , treatment