Karst geology has great influence on the construction and operational maintenance of shieldbored Metro tunnels and cutandcover structures. The karst geological conditions encountered in Guangzhou Metro construction can be divided into high risk area and low risk area. The karst carve in high risk area must be filled up. Taking the design of the karst treatment of the north extension section of No. 3 line of Guangzhou Metro as an example, the author presents the treatment intention, treatment principle, treatment measures, construction attention items and test standards in detail. The karst treatment measures are divided into measures for shield tunnel sections and measures for cutandcover structures.
CLC Number:
U 452.2
LI Guangtao. Design of Karst Treatment: Case Study on North Extension Section of No.3 Line of Guangzhou Metro[J]. Tunnel Construction, 2009, 29(1): 61-64,87.
0 / / Recommend
Add to citation manager EndNote|Ris|BibTeX
URL: http://www.suidaojs.com/EN/B
http://www.suidaojs.com/EN/Y2009/V29/I1/61