ISSN 2096-4498
CN 44-1745/U
Tunnel Construction ›› 2010, Vol. 30 ›› Issue (5): 600-607.
• wenzhang • Previous Articles Next Articles
LIANG Hai-Jing
Received:
Revised:
Online:
Published:
Abstract:
With Xiang'an subsea tunnel in Xiamen as an example, systematic study is made on the advance geological prediction technology, vibrationreducing blasting technology, soft and waterrich surrounding rock treatment technology and mud/ water gushing prevention and control technology during the construction of high risk subsea tunnels. The study results have been applied in the construction of Xiang'an tunnel. A series of safe tunnelling methods suitable for the construction of difficult and high risk large crosssection tunnels under complex geological conditions are summarized, which can provide technical support for the safe construction of similar tunnels in the future.
Key words: subsea tunnel, large crosssection, high risk, "drill and blast", method
LIANG Hai-Jing. Safe "Drill and Blast" Driving Technology for Large Crosssection Subsea Tunnels under Complex Geological Conditions[J]. Tunnel Construction, 2010, 30(5): 600-607.
0 / / Recommend
Add to citation manager EndNote|Ris|BibTeX
URL: http://www.suidaojs.com/EN/
http://www.suidaojs.com/EN/Y2010/V30/I5/600
Application Status and Analysis of Building Information Model (BIM) Technology in Tunnel Engineering
Noise Propagation Characteristics of Tunnel Construction by Drilling and Blasting Method