ISSN 2096-4498

   CN 44-1745/U

二维码

Tunnel Construction ›› 2010, Vol. 30 ›› Issue (S1): 151-155.

• wenzhang • Previous Articles     Next Articles

Study on Ground Surface Settlement Induced by Shield
 Tunneling of Metro Works

 SUN  Hai-Xia1,2, DIAO  Wen2, WANG  Zhao-Yu2, XU  Jian-Jun3   

  1. 1. Shenyang University of Technology, Shenyang 110178;
    2. Northeastern University, Shenyang 110004;
    3. China Railway 9th Bureau Group Co., Ltd., Shenyang 110013
  • Received:2010-03-31 Revised:2010-05-28 Online:2010-08-14 Published:2010-08-25

Abstract:

The ground surface settlement induced by shield tunneling of Metro works is studied on basis of the monitoring results and 3D FEM simulation. The scope of the longitudinal ground surface settlement induced by shield tunneling and the rule of the lateral ground surface settlement are determined. 3D FEM model is established on basis of the actual ground parameters, construction parameters and ground surface settlement data by means of ABAQUS program. The simulated values are compared with the measured values, which indicates that the simulation results are satisfactory. The measured settlement values are within the allowance scope and the simulated values agree well with the measured values. The paper can be served as reference for the prediction of the ground surface settlement of other works in the future.

Key words: ground surface settlement, shield tunneling, monitoring, 3D FEM