ISSN 2096-4498

   CN 44-1745/U

二维码

Tunnel Construction ›› 2011, Vol. 31 ›› Issue (2): 220-227.

• wenzhang • Previous Articles     Next Articles

Comprehensive Technology for Control of Settlement of SpecialshapedPlate Zone: Case Study on Metro Tunnel Crossing Underneath Existing Bridge

WANG Li-Jun1, HU Dun-Wei2   

  1. 1. China Railway Tunnel Stock Co., Ltd., Zhengzhou 450003, China;  2. Technology Center of China Railway Tunnel Group Co., Ltd., Luoyang 471009, Henan, China
  • Received:2010-12-28 Revised:2011-03-20 Online:2011-04-20 Published:2011-05-11

Abstract:

Technologies, such as setting up supporting system on the ground surface, prereinforcing the ground and separating the original piles by means of composite anchors, underpinning by cut piles, pile hole cutting with fullface grouting and bottom grouting, simultaneous lifting of the steel cap, boring parameters optimization, monitoring, simultaneous grouting and supplementary grouting, are adopted to control the settlement of the specialshaped plate zone of the existing bridge. In the end, the difficulties are conquered, the settlement of the existing bridge piles is less than 3 mm and the safety of the tunneling activities and the existing bridge is guaranteed.

Key words: shieldbored tunnel, crossing underneath existing bridge, specialshaped plate, underpinning, settlement control