Tunnel Construction ›› 2011, Vol. 31 ›› Issue (6): 728-732.
• wenzhang • Previous Articles Next Articles
ZHANG Xuewen1, WANG Meng2 ,ZHAO Xupeng1
Received:
Revised:
Online:
Published:
Abstract: The construction of the connection section between No. 3 inclined shaft and main tunnel of Taoshuping tunnel on LanzhouChongqing railway has great construction difficulty, tight construction schedule and high quality requirement. Construction technologies, such as driving the inclined shaft perpendicularly to penetrate the main tunnel, pilot tunneling in the connection section, invert construction of main tunnel, secondary lining of main tunnel, grouting and dewatering are adopted on basis of the geological conditions. In the end, the problem of the construction of the connection section between the inclined shaft and the main tunnel has been successfully solved. The paper can provide theoretical basis and reference for the safe and rapid constriction of similar projects in the future.
Key words: LangzhouChongqing railway, Taoshuping tunnel, bench method, double side drift method
ZHANG Xuewen, WANG Meng,ZHAO Xupeng. Construction Technology for Connection Section between Inclined Shaft and Main Tunnel: Case Study on Taoshuping Tunnel[J]. Tunnel Construction, 2011, 31(6): 728-732.
0 / / Recommend
Add to citation manager EndNote|Ris|BibTeX
URL: http://www.suidaojs.com/EN/
http://www.suidaojs.com/EN/Y2011/V31/I6/728