Abstract: An existing tunnel beneath Terminal 2 building reserved for the Taoyuan International Airport Link Metro Project was enlarged to accommodate the new alignment of Metro rail. The enlargement works were located in boulder formation with ground water head greater than 11.0 meter. The width of enlargement structure varies from 4 m to 18.4 m, and the total excavation volume is 7 927 m3. New thundering earthing system, reinforced strut frames for existing structures and monitoring system were installed to insure the safety and operation of Terminal 2 building. Ground water draw down, double parker grouting and flooding gate erection were performed prior the diamond wire saw demolishment of existing structures. Shotcreting, selfdrilled rockbolt and struts were the main components of the temporary support for excavation faces. This paper describes the details of construction works and the experience gained from this project.
Key words: Taoyuan MRT Airport Line, gravel layer, enlarged excavation tunnel, horizontal dewatering, NATM
ZHANG Wen-Cheng, WANG Qiang-Lin, CHEN Jing-Gong. Construction Cases of MRT Enlarged Excavation Tunnel under Taoyuan Airport Terminal[J]. Tunnel Construction, 2011, 31(S1): 311-316.
0 / / Recommend
Add to citation manager EndNote|Ris|BibTeX
URL: http://www.suidaojs.com/EN/
http://www.suidaojs.com/EN/Y2011/V31/IS1/311
Mechanized Construction Technology for Large Crosssection Longchang Highway Tunnel in Grade Ⅳ Surrounding Rock