Applications and Strategies of ADECORS Approach for Construction of Tunnel Entrance with Shallow Overburden

WANG Shihhui1, LIN Yintan1, WANG Cheinlee2, LEE ChengHaw2   

  1. (1. Raito Engineering Corporation, Taipei; 2. Department of Resources Engineering,National Cheng Kung University, Tainan)
  • Received:2011-04-15 Online:2011-08-05 Published:2011-11-04

Abstract: The growth of environmental protection awareness in Taiwan has made it necessary for tunnel engineers to consider altering the natural surroundings as little as possible when undertaking tunnel design and construction in practice. Tunnel projects in Taiwan have progressively evolved into using the method of direct excavation to replace the traditional method of cut and cover excavation when dealing with tunnel entrances. Even when both the geological and topographical conditions are unfavorable,the method of direct excavation is still adopted because it leads to the lowest environmental impact. The applicability of various methods of direct excavation for tunnel entrances is discussed. These methods include the fore-poling method、the pipe roofing method、the plate shield method and the ground improvement method etc.. The site of a twin road tunnel under construction in northern Taiwan is given as an example. Engineering difficulties and landslide failures at the site are encountered during construction. And, remedial technologies are adopted and evaluated after each failure. It is wishful that the experiences and suggestions can provide worthful references for future tunnel projects facing similar problems in Taiwan.

Key words: ADECO-RS method, tunnel with shallow overburden, pipe-roofing method, NATM