Construction Technologies for Large Crosssection Tunnel Using Mining Method to Enlarge Shield Tunnel

CHEN Ruizheng, HU Weidong*, LI Xinping   

  1. (China Railway Siyuan Survey and Design Group Co., Ltd., Wuhan 430063, Hubei, China)
  • Received:2016-05-09 Revised:2016-07-27 Online:2016-11-20 Published:2016-11-30

Abstract:

The connection section between left line of Line No. 2 of Zhengzhou Metro and connecting tunnel of Line No. 1 and Line No. 2 are constructed together. The surrounding environment is complicated and the construction schedule is tight. The large crosssection tunnel construction technology, mining method, is adopted to enlarge the shield tunnel. The section is bored by shield, and then the steel segments, the bench method of central pillar + temporary invert and inverse enlarging method are adopted. The construction practice shows that the ground settlement and the construction schedule have been controlled effectively. The abovementioned technologies can provide reference for similar projects in the future.

Key words: shield method, mining method, enlargement, bench method, steel segment