Study of Causes and Countermeasure of Excavation Face  Failure of Slurry Shield Tunnel Stopping Section in Expansive Soil:  A Case Study of Slender West Lake Tunnel in Yangzhou

ZHANG Yazhou1,2, ZHU Wei1, 2, CHEN Jian3, MIN Fanlu1,2, SHI Hailing4   

  1. (1. Key Laboratory of Geomechanics and Embankment Engineering (Hohai University), Ministry of  Education, Nanjing 210098, Jiangsu, China; 2. College of Civil and Transportation Engineering,  Hohai University, Nanjing 210098, Jiangsu, China; 3. China Railway 14th Bureau Co., Ltd.,  Jinan 250014, Shandong, China; 4. Architectural Engineering Institute, Nantong Vocational  University, Nantong 226007, Jiangsu, China)
  • Received:2015-08-03 Revised:2015-09-06 Online:2016-05-20 Published:2016-05-25

Abstract:

Excavation face failure and ground surface subsidence occurred at shield stopping section in expansive soil during the construction of Slender West Lake Tunnel. As a result, the expansion test and disintegration test are carried out. The main cause of the excavation face failure and ground surface subsidence, continuous permeation of slurry, is analyzed by site monitoring data and numerical simulation results. The excavation face failure can be divided into 4 phases, i. e. slurry permeating, soil expanding and disintegrating in front of excavation face, soil collapse above excavation face and ground surface subsidence. A series of countermeasures, such as shield boring parameter control, shield stop frequently and transiently, slurry support pressure increasing and slurry improving, are proposed and used. The good effect is achieved.

Key words: Slender West Lake Tunnel in Yangzhou, slurry shield, expansive clay, shield stop, excavation face failure