Key Construction Technologies for Curved Jacking  Pipe Roofing of Gongbei Tunnel

ZHANG Peng1, PAN Jianli2, LIU Yingliang2, MA Baosong1,*   

  1. (1. Faculty of Engineering, China University of Geosciences, Wuhan 430074, Hubei, China; 2. China Railway 18 Bureau Group Co., Ltd., Tianjin 300222, China)
  • Received:2016-02-01 Revised:2016-03-09 Online:2016-08-20 Published:2016-08-17

Abstract:

The construction difficulties of curved jacking pipe roofing of Gongbei Tunnel under complex soft soil, high groundwater pressure and sensitive environment conditions are analyzed. The technologies adopted include pipe jacking machine selection, launching and receiving under high groundwater pressure technology, accuracy control of small span curved jacking, pipeline structure and sealing test and treatment of pipe jacking slurry and obstacles. Good effects have been achieved.

Key words: Gongbei Tunnel, curved jacking pipe roofing, accuracy control, steel sleeve receiving chamber, pipe jacking slurry, relay sleeve method

CLC Number: