Tunnel Construction ›› 2016, Vol. 36 ›› Issue (8): 960-967.DOI: 10.3973/j.issn.1672-741X.2016.08.011
Previous Articles Next Articles
DING Xianli
Received:
Revised:
Online:
Published:
Abstract:
The design and construction of Metro engineering are usually affected by buildings and traffic on the ground, underground pipelines, structures, construction space and geological conditions, etc. As a result, countermeasures are given as follows: 1) The large span noncolumn structure is combined with composite wall structure so as to meet the construction space requirements. 2) The cutandcover topdown method is adopted so as to guarantee the traffic on the ground and replacement of pipelines and improve the safety of foundation pit. 3) The construction schedules of some stations can be guaranteed by using cutandcover topdown method and construction scheme of tunnel first and station followed. Good effects have been achieved.
Key words: Metro project, narrow space, complex factors, cutandcover topdown method, tunnel first and station followed method, optimization design
CLC Number:
U 455
DING Xianli. Design and Construction of South Renminglu Metro Station in Shenzhen under Complex Environment[J]. Tunnel Construction, 2016, 36(8): 960-967.
0 / / Recommend
Add to citation manager EndNote|Ris|BibTeX
URL: http://www.suidaojs.com/EN/10.3973/j.issn.1672-741X.2016.08.011
http://www.suidaojs.com/EN/Y2016/V36/I8/960