Study on Settlement Law of PBA Station of Beijing Metro in Fine Silty Sand Stratum

WU Jingyi1, 2, YE Xinfeng1, 2, *, YU Peng3, TIAN Tengyue4   

  1. (1. Beijing Metro Construction Administration Corporation Ltd., Beijing 100068, China; 2. Beijing Key Laboratory of Automatic Operation System and Safety Monitoring of Urban Rail Transit, Beijing 100068, China; 3. China Railway Engineering Consulting Group Co., Ltd., Beijing 100055, China; 4. China Railway Fifth Survey and Design Institute Group Co., Ltd., Beijing 102600, China) 
  • Online:2020-10-20 Published:2020-11-01

Abstract: The process conversion of PBA method is complex, and it is easy to cause surface settlement. It is difficult to clear the settlement law under different stratum conditions, especially under bad geological conditions such as waterbearing silt formation, which would cause certain safety hazards to the surrounding environment. As a result, the distribution of PBA stations in fine silty sand stratum of Beijing Metro is investigated, the surface settlement laws of PBA station under different precipitation conditions are analyzed based on monitoring data, and the calculation and verification are carried out according to the finite element method. The research results show that: (1) The relationship between occurrence probability of surface settlement value greater than correspondance and maximum surface settlement shows a normal distribution; the maximum surface settlement values of effective precipitation and noneffective precipitation station are -85.31-93.29 mm and -126.16~-131.35 mm, respectively, and the probabilities of the maximum surface settlement value exceeding -60 mm are 53.30% and 74.96%, respectively according to data fitting. (2) The settlement deformation mainly occurs in the construction stage of the pilot tunnel and the arch lining, accounting for about 90%, and the settlement ratio in typical construction stage of top heading excavation,lower bench excavation,beancolumn system construction and arch lining construction is about 4312. (3) The settlement trough is consistent with Peck curve, the settlement trough width is 9.8215.51 m, and the settlement trough width in the effective precipitation station is 35 m wider than that of the noneffective precipitation station. (4) The ground loss rate is 0.56%0.70% generally, and settlement trough width parameter is affected by precipitation effect significantly, ranging from 0.51 to 0.89. The conclusions can be used to preliminarily judge the maximum surface settlement of PBA station

Key words: metro station, PBA method, fine silty sand stratum, settlement, settlement trough