Tunnel Construction ›› 2021, Vol. 41 ›› Issue (3): 474-482.DOI: 10.3973/j.issn.2096-4498.2021.03.017

Previous Articles     Next Articles

Practice and Discussion on Treatment of Ballastless Track Deformation of a HighSpeed Railway Tunnel Caused by Floor Heave Based on Traffic Safety

ZHOU Bao′an1, WU Jian2, WANG Lichuan3, 4, 5, *, GONG Lun4, MA Xiangfeng6, XU Zhaoqiang2, ZHAO Wei5, ZHANG Peng1   

  1. (1.China Railway Chengdu Group Co.,Ltd.,Chengdu 610082,Sichuan,China;2.China Railway Southwest Research Institute Co.,Ltd.,Chengdu 611731,Sichuan,China;3.Central South University, Changsha 410075, Hunan,China;4.Southwest Jiaotong University,Chengdu 610031,Sichuan,China;5.China Railway 18th Bureau Group Co., Ltd.,Tianjin 300222,China;6.China Railway Siyuan Survey and Design Group Co.,Ltd.,Wuhan 430063,Hubei,China)
  • Online:2021-03-20 Published:2021-04-03

Abstract: The bottom heave of an operating highspeed railway tunnel induces deformation of ballastless track, and further affects traffic safety. Accordingly, the driving safety control measures of highspeed railway trains are discussed and some suggestions on the prevention and remediation of tunnel floor heave are put forward based on analysis of the treatment practice process of floor heave of a highspeed railway tunnel. The main conclusions are drawn as follows. (1) The fine adjustment of track along a slope can only relieve the poor track quality caused by floor heaveinduced track deformation temporarily, but cannot eliminate it. (2) If the tunnel is open for operation with bottom heave disease, not only the maintenance workload would be greatly increased, but the operation order would be greatly affected. The optimal rectification time for floor heave is before operation. (3) The prospective and essential way to prevent tunnel floor heave lies in accurate investigation and judgment, targeted design, and strict scientific construction. The practical results show that the treatment scheme with anchoring technology for tunnel floor heave is invalid under MPalevel geostress, whereas an assistant flexiblesupported small crosssection pilot tunnel will be a possible way to prevent tunnel floor heave under large geostress.

Key words: highspeed railway tunnel, tunnel floor heave, ballastless track, railway traffic safety, track fine adjustment along slope, tunnel bottom anchoring