Tunnel Construction ›› 2015, Vol. 35 ›› Issue (S2): 127-130.DOI: 10.3973/j.issn.1672-741X.2015.S2.022
Previous Articles Next Articles
ZHAI Zhiheng
Received:
Revised:
Online:
Published:
Abstract:
In this paper, analysis is made on the ventilation modes for different construction phases, air volume calculation, natural air stress calculation, and air pressurizing under natural air, and the effect of jet ventilation is testified, with the ventilation of AngrenPap superlong tunnel as an example. The results show that jet ventilation mode is rational and can meet construction requirements very well.
Key words: AngrenPap railway tunnel, construction ventilation, jet ventilation, natural ventilation
CLC Number:
U 453.5
ZHAI Zhiheng. Study on Jet Ventilation Technologies for AngrenPap Superlong Tunnel[J]. Tunnel Construction, 2015, 35(S2): 127-130.
/ Recommend
Add to citation manager EndNote|Ris|BibTeX
URL: http://www.suidaojs.com/EN/10.3973/j.issn.1672-741X.2015.S2.022
http://www.suidaojs.com/EN/Y2015/V35/IS2/127
Design and Application of Ventilation Methods for High-Altitude Long-Distance Multi-Working Face Tunnel Construction
Optimization Model for Ventilation Control in Tunnel Construction Based on COAir Demand Theory