Abstract:

According to the soil and sand geological condition in Hankou-Fanhu Section of the 1st phase of Wuhan Metro Line 2 and in combination with the actual cutter configuration for the cutter head of the shield machine, a reasonable modification and configuration plan-replacement of double-edge disc cutter by toothed tooling has been put forward and the structure and the manufacture techniques also have been determined.

Key words: shield,cutter selection, disc cutter, toothed tooling