ISSN 2096-4498
CN 44-1745/U
Tunnel Construction ›› 2010, Vol. 30 ›› Issue (S1): 371-375.
• wenzhang • Previous Articles Next Articles
TANG Chao, HE Shan-Ning
Received:
Revised:
Online:
Published:
Abstract:
The difficulties of the mined section of Beijing Rail Underground Transit Project are analyzed, the optional construction methods are compared and in the end pilebeamarch (PBA) method is adopted. The application of pilebeamarch method in the construction of the urban large crosssection mined tunnel adjacent to buildings is presented. In the end, good results have been achieved.
Key words: large crosssection mined tunnel, pile beam arch (PBA) method, ground surface settlement, deep grouting
TANG Chao, HE Shan-Ning. Construction Technology for Urban Large Crosssection Mined Tunnels Adjacent to Buildings[J]. Tunnel Construction, 2010, 30(S1): 371-375.
0 / / Recommend
Add to citation manager EndNote|Ris|BibTeX
URL: http://www.suidaojs.com/EN/
http://www.suidaojs.com/EN/Y2010/V30/IS1/371