Discussion on Load Calculation Methods of Deepburied Multiarch Tunnels

LI Jingjun1,2, DING Wenqi1,2, WEI Xinxin1,3   

  1. (1. Department of Geotechnical Engineering, Tongji University, Shanghai 200092, China; 2. Key Laboratory of Geotechnical and Underground Engineering of Ministry of Education, Tongji University, Shanghai 200092, China; 3. Sichuan Road & Bridge Construction Company, Chengdu 610041, Sichuan, China)
  • Received:2012-11-07 Revised:2013-03-18 Online:2013-05-20 Published:2013-05-16

Abstract:

In this paper, the authors point out the problems in the existing calculation methods for the vertical loads of deepburied multiarch tunnels. Based on double ground arching method and the method provided in Design Rules of Highway Tunnel, the authors get the corrected load calculation method and the value of the additional correction coefficients. Then the authors make a comparative analysis on the calculation results of vertical loads under the condition of two lane highways and three lane highways. The result obtained by the corrected load calculation method is close to that obtained by the method provided in Design Rules of Highway Tunnel. The corrected load calculation method should be recommended for future application. At last, the formula has been applied in the calculation of the loads of Baziling tunnel and Nashaling tunnel, which demonstrates that the formula is rational.

Key words: deepburied multiarch tunnel, equilibrium arch, correction coefficient, earth pressure, double ground arching method, load calculation