Influence of Hydration Heat on Temperature Field of Metro Jet System Reinforced Test Piles

CHAO Luxin1, FENG Junqing2, YANG Ping1, *, SHI Xin1, YANG Ning2, ZHENG Sheng1   

  1. (1. College of Civil Engineering, Nanjing Forestry University, Nanjing 210037, Jiangsu, China; 2. East China Construction Co., Ltd. of China Railway No.3 Engineering Group Co., Ltd., Nanjing 211106 , Jiangsu, China)
  • Online:2022-04-20 Published:2022-05-01

Abstract: To determine the freezing starting time of the combination reinforcement of the metro jet system(MJS) and horizontal freezing method, the hydration heatrelease law of a MJSreinforced cementsoil test pile is studied. The hydration heat and hydration heatrelease rate of the cementsoil pile with different cement contents (40%, 45%, 50%, 60%, and 70%) are measured using a direct method. Finally, numerical simulations are performed to predict the variation law of the MJS reinforcement temperature field using the data obtained from the hydration heat laboratory tests. A comparative analysis of the simulated prediction and the measured temperature of the MJS test pile from the field is performed. The results reveal the following. (1)The central temperature of the MJS cementsoil test pile increases with the increasing of cementmixing ratio. (2) The change trends of the simulated and measured temperatures of the test pile are similar, validating the numerical simulation. (3) The central temperature of the MJS cementsoil test pile first increases and then decreases gradually; the hydration heatrelease peaks in approximately five days, reaching 56.1~69.2 . Thus, the hydration heat release of the cementsoil pile increases with the increasing of cementmixing ratio. (4) The temperature at the center of the large volume of the cementsoil pile increases due to the hydration effect. The hydration heat release of the MJS cementsoil test pile stops 30 days after construction, indicating that  artificial freezing reinforcement can be conducted.

Key words:  , metro jet system reinforcement, test pile, hydration heat, temperature field, cement soil, artificial freezing reinforcement