Sinking Technology and Industrial Test of FullFace Shaft Boring Machine with Upper Muck Discharge

JIA Lianhui1, XIAO Wei1, LYU Dan1, *, CHENG Jianlin2, HUANG Zhixu2, XU Qiong2   

  1. (1. China Railway Engineering Equipment Group Co., Ltd., Zhengzhou 450000, Henan, China; 2. Zhejiang Ninghai Pumped Storage Co., Ltd., Ningbo 315600, Zhejiang, China)

  • Online:2022-04-20 Published:2022-05-01

Abstract: The traditional drillandblast and shaft sinking methods have limitations in the construction of deep and blind shafts. Accordingly, the mechanized shaft sinking technology of a fullface shaft boring machine(SBM) with upper muck discharge is proposed and studied to realize onetime shaft completion. First, the design concept of the proposed SBM is introduced, and the working principles of the excavation, muck discharge, support, and guidance systems, along with the specific performance parameters of the machine, are introduced. Second, the construction requirements of the starting shaft, equipment assembly sequence, commissioning steps, specific process of shaft section construction, and machine disassembly sequence are extensively described, and the advantages and application prospects of fullface SBM are further summarized. Finally, based on an industrial test of a fullface SBM with upper muck discharge in the shaft construction of the Ninghai pumpedstorage power station, the SBM construction schedule is analyzed, and the corresponding countermeasures for unfavorable geologies are proposed.

Key words:  , upper muck discharge, fullface shaft boring machine, shaft sinking technology, industrial test