Tunnel Construction ›› 2023, Vol. 43 ›› Issue (7): 1246-1256.DOI: 10.3973/j.issn.2096-4498.2023.07.018

Previous Articles     Next Articles

Characteristics Analysis of Debris Flow Disaster in K295 of ChengduKunming Railway and Its Control Countermeasures

LIU Ke1, LI Yunpeng1, LI Yajun1, LUO Shi1, TAN Gang1, CHEN Xitong2, QIU Minjie1, YAO Zhongshan1   

  1. (1. CREEC(Chengdu) Survey, Design and Research Co., Ltd., Chengdu 610031, Sichuan, China; 2. China Railway Chengdu Bureau Group Co., Ltd., Chengdu 610082, Sichuan, China)
  • Online:2023-07-20 Published:2023-08-06

Abstract: A case study is conducted on the K295 debris flow disaster regulation project of the ChengduKunming railway to minimize the risk arising from mountainous railway debris flow and ensure longterm operational safety of the railway. In addition, the situation, scale, zoning, causes, damage extent, and development trend of debris flow disaster are analyzed. Further, a comprehensive debris flow disaster treatment method involving base grouting reinforcement + diversion aqueduct opencut tunnel + tunnel bottom discharge culvert + diversion channel + chute is proposed based on the idea of "focusing on drainage and giving consideration to protection". A technical scheme of prefabrication and assembly of the opencut tunnel arch ring on the existing operating railway is innovatively proposed to ensure normal railway operation during the castinplace construction of the opencut tunnel. Factors such as the onsite terrain, structural safety, and construction period are comprehensively considered. The proposed scheme minimizes the interference between the construction operation and railway transportation and greatly shortens the construction period.

Key words: existing railway, debris flow, diversion channel; prefabrication and assembly, opencut tunnel