ISSN 2096-4498

   CN 44-1745/U

二维码

Tunnel Construction ›› 2006, Vol. 26 ›› Issue (5): 74-75,87.DOI: B

• wenzhang • Previous Articles     Next Articles

Application of “Prestressed Anchor Cable + Antislide
Pile&rdquo|Method in Treatment of Landslides

HAO Yi-Feng   

  1. Division of Technology of Shanxi Provincial Highway Bureau
  • Received:2006-05-09 Revised:2006-08-11 Online:2006-10-20 Published:2010-04-16

Abstract:

The paper presents the “prestressed anchor cable + antislide pile” technology, analyzes the antisliding mechanisms, force bearing characteristics, design principles, design procedures and other relevant issues of the technology and makes technical and economic comparisons between “prestressed anchor cable + antislide pile” and normal antislide piles. The mentioned technology is applied in the treatment of Huangnibao landslide, which demonstrates that the “prestressed anchor cable + antislide pile” is a new generation of antislide structure with broad development future, which is featured by definite force bearing mechanisms, reasonable structure, low cost and convenient for construction.

Key words:  , landslide prestressed anchor cable antislide pile

CLC Number: