Tunnel Construction ›› 2009, Vol. 29 ›› Issue (1): 97-100.DOI: B

• wenzhang • Previous Articles     Next Articles

Construction Scheme Selection for No.4 Inclined Shaft of
Xiangshan Tunnel on LongyanXiamen Railway

LU Huange   

  1. China Railway Tunnel Group Co., Ltd.
  • Received:2009-01-05 Revised:2009-02-01 Online:2009-02-20 Published:2009-11-17

Abstract:

he design scheme of No.4 inclined shaft of Xiangshan Tunnel on LongyanXiamen Railway is optimized according to the actual conditions and construction experiences. The optimized design scheme is compared with the original scheme in terms of technology, safety, construction speed, construction ventilation and economic benefits. The optimized scheme can guarantee the completion of the project on time and can reduce the cost. The paper can provide reference for similar projects in the future.

Key words:  , long tunnelinclined shaftconstruction schemeselection