ISSN 2096-4498

   CN 44-1745/U

二维码

Tunnel Construction ›› 2010, Vol. 30 ›› Issue (1): 33-36.DOI: A

• wenzhang • Previous Articles     Next Articles

Case Study on Optimization Design of Construction Adits of |Xiangshan Tunnel on LongyanXiamen Railway

ZHANG Jian-Ru   

  1. (Project Management Department of ZDI Bid Section of LongyanXiamen Railway, China Railway Tunnel Group Co., Ltd., Longyan 364000, Fujian, China
  • Received:2009-12-10 Revised:2010-01-08 Online:2010-02-20 Published:2010-05-11

Abstract:

 In order to further enhance the transportation capacity and meet the construction ventilation requirements of the inclined shafts of Xiangshan tunnel, the inclined shafts are optimized as follows: the crosssection of No. 1 and No.5 inclined shafs are optimized from 1 lane plus truckmeeting belts into 2 lanes; the gradient of No. 2 inclined shaft is optimized into 22 degree and the length of No. 2 inclined shaft is optimized into 507.98m; the crosssections of No. 3 and No. 4 inclined shafts are optimized from 3 lanes into 4 lanes; No. 5 inclined shaft is optimized to be located on the right side of the tunnel route and is connected to the tunnel route at YDK34+800 with an angle of 42°38′35″, with the gradient of No. 5 inclined shaft being optimized into 9.2%, the length being optimized into 327.5m and the crosssection being optimized into twintrack crosssection. Due to the optimization of these construction adits, the site resources are better utilized and the construction progress is improved. The experience gained in the project is worth to be promoted in similar projects.

Key words: construction adit, inclined shaft, optimization design

CLC Number: