The construction trestle is generally designed by using manual calculation method. The design standard of the manual calculation method depends on checking qualifying of each component. The calculation of and analysis on integral forcing of trestle are limited. In this paper, the MIDAS Civil finite element software is brought in, so as to rationalize the steel trestle structure design of invert construction of Hongtashan Tunnel. After many times of adjustment and calculation, a feasible construction trestle is designed and established, and it is proved to be rational.
Key words: Hongtushan Tunnel, invert, trestle, finite element software
CLC Number:
U 455
LI Zengyin. Design and Application of Trestle in Invert Construction of Hongtushan Tunnel on Yuqu Expressway[J]. Tunnel Construction, 2015, 35(S2): 192-196.
0 / / Recommend
Add to citation manager EndNote|Ris|BibTeX
URL: http://www.suidaojs.com/EN/10.3973/j.issn.1672-741X.2015.S2.035
http://www.suidaojs.com/EN/Y2015/V35/IS2/192