Tunnel Construction ›› 2022, Vol. 42 ›› Issue (9): 1605-1614.DOI: 10.3973/j.issn.2096-4498.2022.09.012

Previous Articles     Next Articles

Research and Application of Assembled Steel Bulkhead for Hanjiang Immersed Tunnel in Xiangyang, China

ZENG Bocun1, CAO Linxiang1, ZHOU Xingtao2, *, SUN Xiaowei1, WANG Cong1, 3, 4, HU Jiayi2   

  1. (1. CCCC Second Harbour Engineering Co., Ltd., Wuhan 430040, Hubei, China; 2. School of Civil Engineering and Architecture, Hubei University of Arts and Science, Xiangyang 441053, Hubei, China; 3. Key Laboratory of Large-span Bridge Construction Technology of Ministry of Communications, Wuhan 430040, Hubei, China; 4. Research and Development Center of Transport Industry of Intelligent Manufacturing Technologies of Transport Infrastructure, Wuhan 430040, Hubei, China)

  • Online:2022-09-20 Published:2022-10-10

Abstract: When installing and dismantling traditional castinplace concrete bulkheads and welded steel bulkheads, the work efficiency is low, and gas pollution is produced. To address these issues, a case study is conducted on the Hanjiang immersed tunnel project in Xiangyang, China, and a novel assembled bulkhead is developed to realize the recycling of bulkhead doors of immersed tunnels. Ethylenepropylenediene monomer rubber strips are installed inside joints between steel bulkhead fragments, and the waterstop function can be realized through the compression deformation of flexible rubber strips. Via indoor tests, the watertightness and compressive stressstrain characteristics of waterstop rubber strips are examined. The structure and installation process of the newly assembled bulkhead are designed, and the onsite monitoring and numerical simulation of its stress and deformation characteristics are performed. The results indicate the following: (1) The maximum horizontal misplacement between the adjacent steel bulkhead and joint width are the key indicators of installation. When the opening between the bulkhead fragment and immersed tunnel element is less than 15 mm, the joint does not leak under a water depth of 40 m. When the horizontal misplacement of the joint between adjacent bulkhead fragments is less than 40 mm and the opening is less than 15 mm, the joint does not leak under a water depth of 30 m. (2) The installation trolley with the functions of traverse walking, deviation correction, lifting, and elevation adjustment is developed to realize space attitude adjustment of the bulkhead fragments quickly. (3) With an increase in the sinking depth of tunnel elements, the bending stress and deformation of the I-shaped steel parts of the bulkhead increase linearly but do not exceed the design values. 

Key words: immersed tunnel, assembled steel bulkhead, waterstop rubber strip, stress, deformation, installation and dismantling procedure