隧道建设(中英文) ›› 2017, Vol. 37 ›› Issue (5): 622-629.DOI: 10.3973/j.issn.1672-741X.2017.05.015

• 施工技术 • 上一篇    下一篇

开敞式TBM隧道仰拱衬砌同步施工关键技术

杨建喜1, 张进2, 李世民3, 张铎1   

  1. (1. 辽宁省水资源管理集团有限责任公司, 辽宁沈阳 110003; 2. 沈阳城市建设学院, 辽宁沈阳 110167;3. 中国水利水电第十四工程局有限公司, 云南昆明 650000)
  • 收稿日期:2017-02-07 修回日期:2017-03-24 出版日期:2017-05-25 发布日期:2017-06-08
  • 作者简介:杨建喜(1985—),男,福建仙游人,2011年毕业于大连理工大学,土木工程管理专业,硕士,工程师,现主要从事水利工程建设管理和技术管理工作。Email: jxyang@foxmail.com。
  • 基金资助:

    辽宁省水利厅科技指导性计划项目(2016-05)

Key Technologies for Synchronous Construction of Inverted Arch Lining of Tunnel Bored by Open TBM

YANG Jianxi1, ZHANG Jin2, LI Shimin3, ZHANG Duo1   

  1. (1. Liaoning Province Water Resources Management Group Co., Ltd., Shenyang 110003, Liaoning, China; 2. Shenyang Urban Construction University, Shenyang 110167, Liaoning, China; 3. Sinohydro Bureau 14 Co., Ltd., Kunming 650000, Yunnan, China)
  • Received:2017-02-07 Revised:2017-03-24 Online:2017-05-25 Published:2017-06-08

摘要:

为实现TBM掘进与仰拱衬砌同步施工,缩短工程关键线路工期,提高隧道施工效率,设计出双通道仰拱同步衬砌台车。台车断面为非对称结构形式,以满足TBM掘进施工及其相关配套设施的布置及运行。台车采取“前斜坡段+前道岔段+4个标准段+后道岔段+后斜坡段”的布置方式,台车下方划分成多个作业面,具备仰拱混凝土浇筑准备、浇筑、养护等的功能;根据施工支洞距离长、坡度大以及TBM掘进段交通条件受限的特点,采用支洞轮式运输和主洞有轨运输的联合运输方式,保障物料运输快捷有序; 台车前后采用升降坡轨道搭接装置,实现TBM配套标准轨道竖向搭接的平顺过渡。工程实践表明: 仰拱同步衬砌台车应用效果较好,施工进度最大可达到648 m/月,在不影响TBM正常掘进的前提下可有效缩短关键线路工期。

关键词: 开敞式TBM, 隧道, 仰拱衬砌, 衬砌台车, 同步施工

Abstract:

In order to implement the synchronous construction of TBM tunneling and inverted arch lining, shorten the critical period of the project and improve the efficiency of tunnel construction, the synchronous lining formework trolley with asymmetrical structural type is designed. The layout mode of “frontal slope section + frontal switch section + 4 standard sections + rear slope section + rear switch section” is adopted for formework trolley. The lower part of the formework trolley is divided into many parts which can provide inverted arch concrete mixing, casting and curing. In accordance with long distance and large slope angle of branch tunnel and limited traffic conditions in TBM section, the connected material transport method of vehicle transport in branch tunnel and track transport in main tunnel is adopted to guarantee the rapid and ordered material transport. A track connecting device for slope lifting is set in front of and behind formework trolley respectively to ensure the smooth transition of vertical connection of standard track of TBM matching. It is shown that the application of formework trolley has reached a good effect, a maximum monthly advance has reached 648 m, and critical period of the project had been shortened.

Key words: open TBM, tunnel, invert arch lining, lining formwork trolley, synchronous construction