Analysis on Conditions for Rapid Boring of Singleshield TBM

YANG Bin   

  1. (China Railway Tunnel Stock Co., Ltd., Zhengzhou 450003, Henan, China)
  • Received:2012-11-26 Revised:2014-06-25 Online:2014-10-20 Published:2014-10-24

Abstract:

Singleshield TBMs have been successfully used in many foreign countries, but there are few such cases in China. No. 7 tunnel of Phase I Works of Tao River Division Project in Gansu, China is bored by a singleshield TBM. In the paper, the construction of the tunnel is presented, and conditions for the rapid boring of singleshield TBM are analyzed in terms of geological conditions, equipment, assistant measures and construction organization.

Key words: singleshield TBM, rapid boring, engineering geological condition, equipment, assistant measure, construction organization