Abstract:
In this paper, the causes and mechanisms of the upfloating of the segment rings of a shieldbored tunnel on No. 7 Line of Guangzhou Metro, which is located in fullface hardrock ground, are analyzed in terms of mechanical conditions and space conditions, so as to ensure the quality of the segment lining. Countermeasures, including pea gravel backfilling behind the segment rings, prevention of gout loss by means of grout stopping rings and waterstopping rings, improving the backfilling effect of the simultaneous grouting by adopting semiopen boring mode, and installing cylinders at the bottom of the front shield to avoid shield pitching, are proposed.
Key words: Guangzhou Metro, shieldbored tunnel, fullface hardrock ground, segment ring upfloating
CLC Number:
U 455.43
YANG Yandong, CHEN Kui, LI Fengyuan, ZHOU Jianjun. Control Technologies for Upfloating of Segment Rings of Shieldbored Tunnel in Fullface Hardrock Ground[J]. Tunnel Construction, 2015, 35(2): 180-184.
0 / / Recommend
Add to citation manager EndNote|Ris|BibTeX
URL: http://www.suidaojs.com/EN/10.3973/j.issn.1672-741X.2015.02.013
http://www.suidaojs.com/EN/Y2015/V35/I2/180