Tunnel Construction ›› 2017, Vol. 37 ›› Issue (S1): 184-188.DOI: 10.3973/j.issn.1672-741X.2017.S1.031
Previous Articles Next Articles
QI Zhichong, HE Fei
Received:
Revised:
Online:
Published:
Abstract:
The components and stepping mechanism of slidingtype stepping system of open TBM are introduced in detail. And then the requirements of slidingtype stepping technology on stepping tunnel, launching tunnel, stepping tunnel of preprocessed bad geological section and maintaining tunnel are summarized. Finally, the operation process of launching and receiving of slidingtype stepping technology, issues should be paid attentions to during stepping and stepping effects are summarized and the advantages and disadvantages of this kind of stepping system are presented. The results can provide references for early infrastructure and TBM stepping of similar projects in the future.
Key words: open TBM, stepping technology, Songhua River Water Diversion Project
CLC Number:
U 45
QI Zhichong, HE Fei. Application of Slidingtype Open TBM Stepping Technology to Songhua River Water Diversion Project[J]. Tunnel Construction, 2017, 37(S1): 184-188.
0 / / Recommend
Add to citation manager EndNote|Ris|BibTeX
URL: http://www.suidaojs.com/EN/10.3973/j.issn.1672-741X.2017.S1.031
http://www.suidaojs.com/EN/Y2017/V37/IS1/184